Solved Example:

9010-01

Pessimistic time and optimistic time of completion of an activity are given as 10 days and 4 days respectively, the variance of the activity will be: (JKSSB JE ME 2015)

Correct Answer: A

Solved Example:

9010-02

In construction project planning, free float can affect which of the following? (CIL MT Civil : 2017)

Correct Answer: D

Solved Example:

9010-03

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is: (GATE ME 2021 Shift II)

Correct Answer: B

Solved Example:

9010-04

The time by which the activity completion time can be delayed without affecting the start of succeeding activities is known as: (SSC JE CE Mar 2017 Evening)

Correct Answer: C

Solved Example:

9010-05

Gantt chats are used for: (MPSC AMVI III: Set A/2011)

Correct Answer: B

Solved Example:

9010-06

A point which represents either starting or termination of activity is known as _______.(UPRVUNL AE ME July 2022)

Correct Answer: C

Solved Example:

9010-07

Dangling phenomenon in a network diagram: (UPRVUNL AE ME Shift I Jul 2022)

Correct Answer: B

Solved Example:

9010-08

In a network diagram, an activity having a dotted arrow between activities is often referred to as a/an ________ activity. (UPRVUNL AE ME Shift I July 2022)

Correct Answer: D